The restoration of the Århus Å, 19 May 2007
iWork on the restoration of the Århus Å is progressing. The bridge over the Immervad was recently reopened. Unlike the other bridges along the newly opened stretch, this bridge is constructed of concrete.
The bridge is a fairly large structure, as a long series of telecommunications cables, as well as two large district heating pipes, have to cross the river here. Nevertheless, the bridge manages to appear very slender, as it tapers towards the natural viewing angles.
iWhen the old stone bridge was demolished as part of the work to cover the stream, the stones were stored away. It had been hoped that the old bridge could be rebuilt, but following its transfer between municipal storage sites, as well as exposure to the elements, a large proportion of the stones had gone missing, and the remaining ones had lost their markings.
Nevertheless, some of the stones have been used for the bridge’s southern foundation.
iWork on the south side of Åboulevarden is progressing. The work was hampered by the winter and the subsequent flooding. Furthermore, archaeological excavations and misplaced cables have delayed the work. It is expected that the section from Busgaden to Immervad will be completed before the Tall Ships Race in July 2007. However, the central wall will not be removed until the end of the year. Work from Busgaden and westwards is expected to be completed by the end of the year.
iThe northernmost section of Frederiksgade is being repaved using the same types of stone as the rest of the area. Work has been underway for some time at Telefontorvet, and is now continuing down towards the river.
The work has been delayed due to a lack of granite deliveries, but it is expected to be completed by August 2007.
The entire Telefontorvet, Frederiksgade down to the river, the southern side of Åboulevarden, and approximately 25 metres down Fiskergade are being resurfaced.